Files

3.3 KiB
Raw Permalink Blame History

Texas Mechanic's Lien — Quick Reference

Authority: Texas Property Code Chapter 53

Who Can File

  • Original Contractor (GC): Direct contract with owner — no pre-lien notice required
  • Subcontractor: Hired by GC — must send pre-lien notice within 15 days
  • Material Supplier: Must send notice if not under direct contract with owner
  • Laborer: Eligible with simplified notice
  • Design Professional: Architect/engineer — written notice required if not under direct contract

Who CANNOT File

  • Unlicensed contractors (Texas Occupations Code Ch. 1301/1305/1306)
  • Remote suppliers (suppliers to suppliers — too far from the project)
  • Finance-only parties (lenders, banks with no construction involvement)

Critical Deadlines

Role File Lien By Statute
GC 15th day of 4th month after month of completion § 53.052
Sub/Supplier 15th day of 3rd month after month of completion § 53.052
Foreclosure suit Within 1 year of last day to file § 53.158

All deadlines count from MONTH of project completion, not day. Example: completion in March → GC deadline is July 15.

Pre-Lien Notices

Scenario Deadline Consequence if Missed
Sub notice to owner (commercial) Within 15 days of first furnishing Lien limited to retainage
Sub monthly notice (residential) By 15th of 2nd month after work month Complete loss of lien rights
Notice of filed affidavit Within 5 days of filing Lien invalid against owner
Homestead written contract Before work, signed by both spouses Lien void

Homestead

  • Art. XVI § 50 of Texas Constitution
  • Written contract required, signed by both spouses
  • Lien must state: "This is a lien on homestead"
  • 3-year redemption period after foreclosure sale
  • Avoid for claims under $25K

No Lien on Public Projects

Use bond claims instead:

  • McGarr Act (TX Gov't Code Ch. 2253): 90-day notice, 1-year suit
  • Miller Act (40 USC §§ 31313134): federal projects

FDCPA / DRE Restrictions

  • DRE cannot file liens directly — UPL + FDCPA violation
  • DRE can send pre-lien notices (factual, template-based, with Mini-Miranda)
  • Actual lien filing requires licensed Texas construction attorney
  • Wrongful lien damages: TX Prop. Code § 53.152 — actual + fees + up to $10K exemplary

Tier 2.5 Workflow (DRE Recovery Progression)

  1. Phase A (DRE-led): Pre-lien notice via certified mail to owner + GC + lender
  2. Phase B (Attorney-led): Refer to construction attorney for lien affidavit filing
  3. Phase C (Monitor): If no payment, escalate to foreclosure if claim ≥ $10K

Minimum Thresholds

  • Pre-lien notice: $1,000
  • Lien filing: $2,500
  • Foreclosure: $10,000

Key Cases

Case Holding
First Nat'l Bank v. Whirlpool Corp., 517 S.W.2d 262 Relation-back: lien priority dates to visible commencement of work
McCollough v. Johnson, Rodenburg & Lauinger, 637 F.3d 939 FDCPA applies to time-barred debt threats
H&M Steel, LLC v. HRR Asset Mgmt, 2015 Strict enforcement of lien deadlines

Full report: /root/Texas_Mechanics_Lien_Research_Report.md Compliance manual section: DRE_Compliance_Manual.md § 22 — Mechanic's Lien & Bond Claims (Tier 2.5)