# Texas Mechanic's Lien — Quick Reference
|
||||
|
||||
## Authority: Texas Property Code Chapter 53
|
||||
|
||||
## Who Can File
|
||||
- **Original Contractor (GC):** Direct contract with owner — no pre-lien notice required
|
||||
- **Subcontractor:** Hired by GC — must send pre-lien notice within 15 days
|
||||
- **Material Supplier:** Must send notice if not under direct contract with owner
|
||||
- **Laborer:** Eligible with simplified notice
|
||||
- **Design Professional:** Architect/engineer — written notice required if not under direct contract
|
||||
|
||||
## Who CANNOT File
|
||||
- Unlicensed contractors (Texas Occupations Code Ch. 1301/1305/1306)
|
||||
- Remote suppliers (suppliers to suppliers — too far from the project)
|
||||
- Finance-only parties (lenders, banks with no construction involvement)
|
||||
|
||||
## Critical Deadlines
|
||||
| Role | File Lien By | Statute |
|
||||
|------|-------------|---------|
|
||||
| **GC** | 15th day of 4th month after month of completion | § 53.052 |
|
||||
| **Sub/Supplier** | 15th day of 3rd month after month of completion | § 53.052 |
|
||||
| **Foreclosure suit** | Within 1 year of last day to file | § 53.158 |
|
||||
|
||||
All deadlines count from MONTH of project completion, not day. Example: completion in March → GC deadline is July 15.
|
||||
|
||||
## Pre-Lien Notices
|
||||
| Scenario | Deadline | Consequence if Missed |
|
||||
|----------|----------|----------------------|
|
||||
| Sub notice to owner (commercial) | Within 15 days of first furnishing | Lien limited to retainage |
|
||||
| Sub monthly notice (residential) | By 15th of 2nd month after work month | Complete loss of lien rights |
|
||||
| Notice of filed affidavit | Within 5 days of filing | Lien invalid against owner |
|
||||
| Homestead written contract | Before work, signed by both spouses | Lien void |
|
||||
|
||||
## Homestead
|
||||
- Art. XVI § 50 of Texas Constitution
|
||||
- Written contract required, signed by both spouses
|
||||
- Lien must state: "This is a lien on homestead"
|
||||
- 3-year redemption period after foreclosure sale
|
||||
- Avoid for claims under $25K
|
||||
|
||||
## No Lien on Public Projects
|
||||
Use bond claims instead:
|
||||
- **McGarr Act** (TX Gov't Code Ch. 2253): 90-day notice, 1-year suit
|
||||
- **Miller Act** (40 USC §§ 3131–3134): federal projects
|
||||
|
||||
## FDCPA / DRE Restrictions
|
||||
- **DRE cannot file liens directly** — UPL + FDCPA violation
|
||||
- DRE can send pre-lien notices (factual, template-based, with Mini-Miranda)
|
||||
- Actual lien filing requires licensed Texas construction attorney
|
||||
- Wrongful lien damages: TX Prop. Code § 53.152 — actual + fees + up to $10K exemplary
|
||||
|
||||
## Tier 2.5 Workflow (DRE Recovery Progression)
|
||||
1. **Phase A (DRE-led):** Pre-lien notice via certified mail to owner + GC + lender
|
||||
2. **Phase B (Attorney-led):** Refer to construction attorney for lien affidavit filing
|
||||
3. **Phase C (Monitor):** If no payment, escalate to foreclosure if claim ≥ $10K
|
||||
|
||||
## Minimum Thresholds
|
||||
- Pre-lien notice: **$1,000**
|
||||
- Lien filing: **$2,500**
|
||||
- Foreclosure: **$10,000**
|
||||
|
||||
## Key Cases
|
||||
| Case | Holding |
|
||||
|------|---------|
|
||||
| *First Nat'l Bank v. Whirlpool Corp.*, 517 S.W.2d 262 | Relation-back: lien priority dates to visible commencement of work |
|
||||
| *McCollough v. Johnson, Rodenburg & Lauinger*, 637 F.3d 939 | FDCPA applies to time-barred debt threats |
|
||||
| *H&M Steel, LLC v. HRR Asset Mgmt*, 2015 | Strict enforcement of lien deadlines |
|
||||
|
||||
**Full report:** `/root/Texas_Mechanics_Lien_Research_Report.md`
|
||||
**Compliance manual section:** `DRE_Compliance_Manual.md` § 22 — Mechanic's Lien & Bond Claims (Tier 2.5)
|
||||