# Texas Mechanic's Lien — Quick Reference ## Authority: Texas Property Code Chapter 53 ## Who Can File - **Original Contractor (GC):** Direct contract with owner — no pre-lien notice required - **Subcontractor:** Hired by GC — must send pre-lien notice within 15 days - **Material Supplier:** Must send notice if not under direct contract with owner - **Laborer:** Eligible with simplified notice - **Design Professional:** Architect/engineer — written notice required if not under direct contract ## Who CANNOT File - Unlicensed contractors (Texas Occupations Code Ch. 1301/1305/1306) - Remote suppliers (suppliers to suppliers — too far from the project) - Finance-only parties (lenders, banks with no construction involvement) ## Critical Deadlines | Role | File Lien By | Statute | |------|-------------|---------| | **GC** | 15th day of 4th month after month of completion | § 53.052 | | **Sub/Supplier** | 15th day of 3rd month after month of completion | § 53.052 | | **Foreclosure suit** | Within 1 year of last day to file | § 53.158 | All deadlines count from MONTH of project completion, not day. Example: completion in March → GC deadline is July 15. ## Pre-Lien Notices | Scenario | Deadline | Consequence if Missed | |----------|----------|----------------------| | Sub notice to owner (commercial) | Within 15 days of first furnishing | Lien limited to retainage | | Sub monthly notice (residential) | By 15th of 2nd month after work month | Complete loss of lien rights | | Notice of filed affidavit | Within 5 days of filing | Lien invalid against owner | | Homestead written contract | Before work, signed by both spouses | Lien void | ## Homestead - Art. XVI § 50 of Texas Constitution - Written contract required, signed by both spouses - Lien must state: "This is a lien on homestead" - 3-year redemption period after foreclosure sale - Avoid for claims under $25K ## No Lien on Public Projects Use bond claims instead: - **McGarr Act** (TX Gov't Code Ch. 2253): 90-day notice, 1-year suit - **Miller Act** (40 USC §§ 3131–3134): federal projects ## FDCPA / DRE Restrictions - **DRE cannot file liens directly** — UPL + FDCPA violation - DRE can send pre-lien notices (factual, template-based, with Mini-Miranda) - Actual lien filing requires licensed Texas construction attorney - Wrongful lien damages: TX Prop. Code § 53.152 — actual + fees + up to $10K exemplary ## Tier 2.5 Workflow (DRE Recovery Progression) 1. **Phase A (DRE-led):** Pre-lien notice via certified mail to owner + GC + lender 2. **Phase B (Attorney-led):** Refer to construction attorney for lien affidavit filing 3. **Phase C (Monitor):** If no payment, escalate to foreclosure if claim ≥ $10K ## Minimum Thresholds - Pre-lien notice: **$1,000** - Lien filing: **$2,500** - Foreclosure: **$10,000** ## Key Cases | Case | Holding | |------|---------| | *First Nat'l Bank v. Whirlpool Corp.*, 517 S.W.2d 262 | Relation-back: lien priority dates to visible commencement of work | | *McCollough v. Johnson, Rodenburg & Lauinger*, 637 F.3d 939 | FDCPA applies to time-barred debt threats | | *H&M Steel, LLC v. HRR Asset Mgmt*, 2015 | Strict enforcement of lien deadlines | **Full report:** `/root/Texas_Mechanics_Lien_Research_Report.md` **Compliance manual section:** `DRE_Compliance_Manual.md` § 22 — Mechanic's Lien & Bond Claims (Tier 2.5)